| “ITAQUI” PORT THERMAL ELECTRIC POWER PLANT (in progress)Main civil works for a coal thermal electric power plant.
- Power: 360 MW - Structural concrete: 36,672 m³ - Concrete paving: 7,561 m³ - Inserts: 180 ton
|
Locality: São Luis – Maranhão Owner: MABE Construção e Administração de Projetos Ltda
|

| “PAIOL” DAM
Complete civil works for the “Paiol” Dam, a small hydroelectric power plant, located on “Suaçuí Grande” River.
- Power: 20 MW - Earth-fill Dam: 65,000 m³ - Soil excavation: 91,829 m³ - Rock excavation: 120,405 m³ - Structural concrete: 24,949 m³ |
Locality: Frei Inocêncio e Mathias Lobato - Minas Gerais Owner: Paiol Energia S.A. (ERSA - Energias Renováveis)
|

| “ARVOREDO” DAMComplete civil works for the “Arvoredo” Dam, a small hydroelectric power plant, located on “Irani” River.
- Power: 13.5 MW - Rolled compacted concrete dam: 53,000 m³ - Soil and rock excavation: 237,000 m³ - Structural concrete: 28,800 m³
|
Locality: "Irani" River - Santa Catarina Owner: SPE Arvoredo Energia S.A.
|

| “BARRA DO BRAÚNA” DAMEPC / Turnkey Lump Sum contract for construction of “Barra do Braúna” Dam, a hydroelectric power plant, located on “Pomba” River.
- Power: 39 MW - Earth-fill dam and riprap: 500,000 m³ - Soil and rock excavation: 618,000 m³ - Structural concrete: 45,000 m³
|
Locality: Recreio - Minas Gerais Owner: Barra do Braúna Energética S.A.
|

| “SANTA FÉ” DAMEPC contracto for construction of “Santa Fé” Dam, a small thermo electric power plant, located on “Itapemirim” River.
- Power: 29.6 MW - Structural concrete: 32,000 m³ - Rock excavation: 705,500 m³ - Underground rock excavation: 84,700 m³ - Soil excavation: 280,000 m³
|
Locality: "Itapemirim" River – Alegre - Espírito Santo Owner: Santa Fé Energia S.A. – Energias do Brasil
|

| “CAÇU” AND “COQUEIROS” ENERGY COMPLEXComplete civil works for the construction of two hydroelectric power plants in “Goiás”, State of Brazil. With a total power of 155 MW, “Caçu” has 65 MW and “Coqueiros” has 90 MW, this complex could provide energy for more than 500,000 inhabitants. Consortium: Cesbe and Toniolo Busnello.
|
| | Locality: Caçu e Cachoeira Alta - Goiás Owner: Gerdau Aços Longos S.A.
|

| THERMAL ELECTRIC POWER PLANT FOR THYSSENKRUPP CSAThe ThyssenKrupp CSA are building a new steel mill in Sepetiba Bay in the state of Rio de Janeiro in Brazil. The mill will have an annual capacity of five million tons of steel and will commence production in summer 2010. We did the civil works for the Thermal Electric Power Plant that will provide energy for the complex. - Power: 490 MW - Structural concrete: 24,412.13 m³ - Jet Grouting columns Ø 140 cm: 10,191 m - Inserts: 105 ton
|
| | Locality: Sepetiba - Rio de Janeiro Owner: Alstom Brasil Energia e Transporte Ltda
|

| USIMINAS THERMAL ELECTRIC POWER PLANTMain civil works for the thermal electric power plant (unit 02) for Usiminas “Intendente Câmara” Plant.
- Structural concrete: 5,041 m³ - Inserts: 18.23 ton
|
| | Locality: Ipatinga - Minas Gerais Owner: CONSTRUÇÕES E COMÉRCIO CAMARGO CORRÊA S.A.
|

| DA ILHA DAM
This EPC / turnkey contract also profited from the small dams proximity - Da Ilha and Jararaca - by allowing simultaneous construction with a unified management which greatly reduced costs.
- Rolled compacted concrete dam: 50,000 m³ - Rock excavated tunnel: 2,070 m long with 50.4 m² cross section - Power: 26 MW - Soil and rock excavation: 158,000 m³ - Structural concrete: 19,700 m³
|
| | Locality: "da Prata" River - Rio Grande do Sul Owner: DA ILHA ENERGÉTICA S.A.
|

| JARARACA DAM
Turnkey project located on "da Prata" River – RS. - Rolled compacted concrete dam: 40,000 m³ - Rock excavated tunnel: 1,110 m long with 50.4 m² cross section - Power: 28 MW - Soil and rock excavation: 201,000 m³ - Structural concrete: 19,300 m³
|
| | Locality: "da Prata" River - Rio Grande do Sul Owner: VÊNETO ENERGÉTICA S.A.
|

| ALTO IRANI DAM
Turnkey project located on "Irani" River.
-Clay core rock fill dam: 362,000 m³ -Rock excavated tunnel: 1,830 m long with 22.4 m² cross section -Power: 21 MW -Soil and rock excavation: 660,000 m³ -Structural concrete: 13,900 m³
|
| | Locality: "Irani" River - Santa Catarina Owner: SPE Alto Irani Energia S.A.
|

| PLANO ALTO DAM
The proximity of the small dams - Plano Alto and Alto Irani – allowed this turnkey project to be simultaneously constructed by a unified staff with noteworthy cost reduction.
- Rolled compacted concrete dam: 42,000 m³ - Rock excavated tunnel: 230 m long with 16 m² cross section - Power: 16.2 MW - Soil and rock excavation: 165,000 m³ - Structural concrete: 14,500 m³
|
| | Locality: "Irani" River - Santa Catarina Owner: SPE Plano Alto Energia S.A.
|

| BURITI DAM
Turnkey project located on "Sucuriú" River.
- Clay core rock fill dam - CCR. - Power: 30 MW - Soil and rock excavation: 350,000 m³ - Structural concrete: 21,500 m³
|
| | Locality: "Sucuriú" River - Mato Grosso do Sul Owner: Pouso Alto Energia LTDA
|

| CARLOS GONZATTO DAMComplete civil works for the Carlos Gonzatto Dam, with 9 MW of total power capacity. The owner is Campo Novo Energia S.A. (a company of CESBE´s Group).
|
| | Locality: "Turvo" River - Rio Grande do Sul Owner: CN Energia S.A.
|

| PARANATINGA DAM
Turnkey project located on "Coluene" River. - Clay core rock fill dam - 351,000 m³ - Power: 30 MW - Soil and rock excavation: 580,000 m³ - Structural concrete: 32,000 m³
|
| | Locality: "Coluene" River - Mato Grosso Owner: Paranatinga Energia LTDA
|

| AÇU THERMAL ELECTRIC POWER PLANT
Phase one civil works: construction of two power islands for equipment bases; foundations for steel tanks; and underground concrete channel.
- Power: 340 MW - Structural concrete: 10,500 m³ |
| | Locality: Açu - Rio Grande do Norte Owner: Petróleo Brasileiro S.A. - Petrobras
|

| PIRATININGA THERMAL ELECTRIC POWER PLANT
Civil works construction including Management, Operations and Maintenance Buildings.
- Power: 400 MW - Structural concrete: 17, 000 m³ - Electric envelope / pipeline: 265 ton - Inserts: 295 ton
|
| | Locality: São Paulo – Capital Owner: Petróleo Brasileiro S.A. - Petrobras
|

| ITAIPU POWER PLANT
CESBE was the leading company responsible for the installation of the last two Itaipu’s power units. The Consortium executed the services with the power plant in operation.
- Power supplied by the two units: 1,400 MW - Structural concrete: 50,000 m³
|
| | Locality: "Paraná" River – Paraná | Border Brasil – Paraguai Owner: Itaipu Binacional
|

| “URUGUAIANA” THERMAL ELECTRIC POWER PLANTSome civil works for “Uruguaiana” thermal electric power plant (gas), including underground systems, tanks and dikes.
- Power: 639 MW
|
| | Locality: Uruguaiana – Rio Grande do Sul Owner: AES/SIEMENS-WESTING-HOUSE/PROMON
|

| SEGREDO POWER PLANT
River Deviation: Cesbe participated in the Construction of three tunnels - cross section: 163 m² - for the deviation of the Iguaçu River. Total length: 2.115,355 m. Main Works: Excavations in soil and rock for structures; Rock fill dam with concrete face-height; Concrete structures for Spilway, Water intake, Penstock and Power House. Installed power: 1.260 MW.
Summary of quantities: Rockfill: 5, 800, 000 m³ Rock excavation: 7, 300, 000 m³ Reinforced concrete: 300, 000 m³ Reinforcement bars: 27, 000 t Steel structures, stel pipes and fittings: 745, 000 t
|
| | Locality: "Iguaçu" River - Paraná Owner: Companhia Paranaense de Energia - Copel
|